| Wed Jun 15, 2011 | Post #1 | S L Gupta (Civil Engg)

Join date: Mar 2008 | Dear Rao
For brick work curing should be commence within 12 hours in case of cement sand mortar and continue at least minimum for 7 days but in case of rich mortar 1:4 and more curing should be done for 10 days.
For cement plaster curing should be started 24 hours after finishing and kept wet for 7 days . for more information about construction you should visit website gharexpert.com where lot of material are available about construction. | | |
|
|